PHASE WISE JOURNEY
Feasibility Study
This is the First Phase of a Redevelopment Project.
It starts when a Society’s managing Committee (MC) initiates the Process of Redevelopment through a General Body Meeting and ends when a Feasibility Report prepared by the PMC is formally adopted by the Society’s General Body. This period consists of the following two stages and may be about 4 months:
Stage 1: Initiating Project & Appointing PMC:
Active Agency: MC
Period: 2 months
SGBM: 1
Milestones:
- Resolution for Redevelopment
- Appointment of PMC
Project Records: PMC’s Letter of Appointment
Stage 2: Feasibility Study & Report:
Active Agencies: MC, PMC
Period: 2 months
SGBMs: 2
Milestones:
- Finalization of Base Carpet Area
- Approval of Feasibility Report
Project Records:
- Base Carpet Areas
- Feasibility Report
After the Feasibility Report is approved in a General Body Meeting, the Project will move to the next Phase of Tendering & Developer Selection.