Roadmap >> Preparations
Download Short Notes

Abbreviations: (Secretary - Sec, Member/s - Mem, Milestone - M, Record - R, Guideposts - GP)
Sr. No.StepByParticularsM/ R/ G
1Issue LOI to Selected Dev MC LOI is to be issued to Selected Dev after NOC is received from Dy. Registrar.

For Suggested content of LOI, refer to Guidepost.
M, R & GP
2Submit Letter of Acceptance of LOI to MC Dev Dev should submit Acceptance of LOI to MC together with release of payments/ deposits due at that stage. R
3Establish FSI Potential of the Plot Dev Obtain latest Property docs, NOCs, Remarks, Permissions etc and establish the FSI Potential.
4Finalize Work Specs, Lists of Internal, Common & Built Amenities MC, Dev, PMC Area wise list of Work Specs and Amenities should be prepared. The same shall become a part of DA.

For Suggested List of Work Specs and Amenities, refer to Guidepost.
R & GP
5Technical Due Diligence MC May cover Structural Design Basis Report (DBR), Geotechnical Report (GTR), Finished Ground Level & Plinth Levels