Roadmap >> Plans & Approvals/ Permissions
Download Short Notes

Abbreviations: (Secretary - Sec, Member/s - Mem, Milestone - M, Record - R, Guideposts - GP)
Sr. No.StepByParticularsM/ R/ G
1Submit Initial Architectural Plans to MC & PMC Dev At this stage, Dev's Architect shall provide tentative plans. These plans shall mainly show Members Units for Soc's approval. CAD and PDF files should be submitted.

For Suggested Contents of Initial Architectural Plans, refer to Guidepost
GP
2Review Arch Plans PMC, MC Plans to be reviewed w.r.t. Specs and requirements specified in DA/ Tender Docs. Remarks/ suggestions to be sent to Dev.

For Suggested Checkpoints for Review of Initial Plans, refer to Guidepost.
GP
3Submit Revised Arch Plans to MC & PMC Dev Dev should incorporate Soc/ PMC’s remarks/ suggestions and provide CAD and PDF files.
4Review Revised Arch Plans PMC, MC To check whether remarks/ suggestions sent earlier have been incorporated. To Recheck: Carpet Areas of Members’ units, Car Parks, Floor heights, FSI statement. Further remarks/ suggestions may be sent to Dev, who shall revise the plans again, if necessary, until they are acceptable to both.
5Finalization of Arch Plans by MC MC This Finalization is mainly for the Members’ units, Amenities, Car parks and Floor heights. MC shall convey such approval to Dev. Thereafter, Dev shall prepare Detailed Proposal Plans for Statutory approvals/ permissions. M & R
6Submit Detailed Proposal Plans to MC & PMC Dev These plans should be complete in all respects as per the requirements of the Approving Authorities. CAD and PDF files should be submitted.

For Suggested Contents of Proposal Plans, refer to Guidepost.
GP
7Checking of Proposal Plans PMC, MC Plans to be reviewed w.r.t. Specs and requirements specified in DA/ Tender Docs and earlier Remarks/ suggestions. Any error/ inconsistency should be informed to Dev for rectification, and the plans shall be rectified until they are acceptable to Soc. For Suggested Checkpoints for Review of Proposal Plans, refer to Guidepost. GP
8Submit Report on Proposal Plans to MC PMC Report shall be based on the Checkpoints which are already given for Checking of Proposal Plans and deviations, if any, should be brought out. R
9Allot Members’ Units MC Units may be allotted in accordance with any generally accepted method or by lottery as per the common choice of members. Method of allotment may also depend upon the configuration of Existing bldg/s and the units within them.
10Send Notice to Members for SGBM8 MC Agenda: Dev’s Presentation on Proposal Plans to members, Approval of Proposal Plans and confirmation of Allotment of Members’ units.
11SGBM8 - Approval of Proposal Plans & Allotment GB The Proposal Plans, Allotment Members' Units shall be approved. Terms of payment for purchase of extra Carpet Area may also be approved, however the transactions shall be between the Dev and concerned members only.

Resolutions to be passed:
1. Approval of Proposal Plans
2. Approval of Allotment
M & R
12Convey Approval of Proposal Plans to Dev MC This approval will entitle the Dev to submit plans to Statutory Authorities and to obtain their approvals/ permissions.
13Send MoM to members Sec Within 7 days from SGBM8.
14Send MoM to Dy. Registrar Sec Within 15 days from SGBM8.
15Submit Plans to Statutory Authorities Dev Dev shall submit Plans to Statutory Authorities for Approvals/ Permissions. Only those plans which have been approved by Soc shall be submitted. If any revision is required to be made in the plan during the process of approval, as suggested by any Approving Authority, the same shall be referred to MC before its incorporation. M
16Obtain & Report Approvals/ Permissions of Plans Dev Such Approvals/ permissions may come in multiple stages. As and when a stage is reached, Dev shall Report to the MC & PMC accordingly. Some stages may be tracked on the website of the Approving Authorities. M & R
17Verify Approved Plans PMC Plans approved by Statutory Authorities should be checked and verified with the plans approved by Soc in their SGBM
18Track Process of Plans & Approvals PMC Milestones based Tracking wrt Time Schedule mentioned in LOI/ DA.
19Upload Progress on Soc Website MC Progress of work may be uploaded on Soc’s Website from time to time.