Roadmap >> Vacating Units
Download Short Notes

Abbreviations: (Secretary - Sec, Member/s - Mem, Milestone - M, Record - R, Guideposts - GP)
Sr. No.StepByParticularsM/ R/ G
1Submit necessary Approvals/ Permissions and Approved Plans Dev Should be submitted to MC. The Approvals/ Permissions should be unconditional. MC/ PMC shall check the Approvals/ Permissions & Approved Plans.
2Execute and Register PAAA Dev, Mem This includes payment of Stamp duty and Registration by Dev. M & R
3Complete all requirements for vacating premises Dev The conditions which are specified in DA for vacating of premises should be fulfilled before Dev issues a notice to vacate. MC/ PMC shall check fulfillment of such conditions.

For Suggested Conditions for Vacating Premises, refer to Guidepost.
GP
4Issue Notice to Vacate premises Dev Dev shall handover all instruments of payment for members to MC along with the Notice. R
5Make Agreed Payments to Members & Soc Dev/ MC Payments such as: Rent, Corpus, Brokerage, Shifting Charges, Professional fees, Misc. Expenses etc.
6Vacate Existing Units Mem All members should vacate their respective units up to the end of Notice Period.
7Submit other Project Docs to MC Dev Docs such as: Detailed Project Schedule with Milestones which shall be used to monitor & track Progress of work and Project Insurance which should cover the entire project including Workmen's Compensation & Third Party Cover. R
8Issue Letter to Enter to Dev MC Authorizing Giving Possession to the Dev to disconnect all Services in the Existing Bldg/s, Demolish them and Start construction of New bldg/s. The Letter may have certain conditions pertaining to the Dev's obligations depending of the provisions of DA. M & R
9Submit Letter of Acceptance of LTE to MC Dev The Dev should formally convey his acceptance of LTE and fulfill the conditions which are specified in DA at this stage. R
10Demolish Existing Bldg/s Dev
11Obtain Commencement Certificate Dev Soft & Hard Copy of CC to be provided to MC and PMC. M
12Register the Project in RERA Dev Soft & Hard Copy of Registration Certificate to be provided to MC and PMC. R
13Track Process of Vacating stage PMC Milestones based Tracking wrt Time Schedule mentioned in DA.
14Upload Progress on Soc Website MC Progress of work may be uploaded on Soc’s Website from time to time.