PHASE WISE JOURNEY
Sr. No. | Step | By | Particulars | M/ R/ G |
---|---|---|---|---|
1 | Conduct Site Visits | PMC | PMC's Project Co-ordinator shall conduct Joint Site Visits (SV) along with DST and SCT, if necessary. These Site Visits may be conducted Weekly. For suggested Checkpoints for such Site Visits, refer to Guidepost. | GP |
2 | Submit SV Report to MC | PMC | The Observations/ Discussions/ Decisions taken in the Site Visit should be recorded in a Site Visit Report (SVR), which PMC shall submit to Soc. For suggested Contents of a Site Visit Report, refer to Guidepost. | R & GP |
3 | Conduct Joint Project Review Meetings | PMC | Such joint Project Review Meetings (PRM) may be held periodically, e.g. once a month and should be attended by Soc MC and senior representatives of Dev and PMC. For suggested Agenda for such PRM, refer to Guidepost. | GP |
4 | Send PRM Minutes to MC and Dev | PMC | MoM should be prepared by PMC and sent to MC & Dev. For suggested Contents of Minutes of PRM, refer to Guidepost. | R & GP |
5 | Send Project Review Report to MC | PMC | PMC should prepare a detailed Project Review Report and submit to Soc. Suggested frequency - Monthly For suggested Contents of Project Review Report, refer to Guidepost. | R & GP |
6 | Check Quality of Ongoing Work | PMC | Quality to be checked by PMC’s Site Engineer w.r.t. Working Drawings and Specs of Materials mentioned in DA/ Tender Docs. Any defect or deficiency observed should be conveyed to DST for rectification or corrective action. | |
7 | Check Material Test Reports | PMC | PMC shall check Test Reports as and when they are received from the DST. Any deficiency, failure or unacceptable observation should be conveyed to DST for further testing, rectification or corrective action. It may also be necessary to demolish the concerned work. | |
8 | Check Concrete Cube Test Reports | PMC | PMC shall check Cube Test Reports periodically and at important stages. Any deficiency, failure or unacceptable observation should be conveyed to DST for further testing, rectification or corrective action. It may also be necessary to demolish the concerned work. | |
9 | Intimate Defects in work to Dev | PMC | If any defect in quality or deviation from specifications or deficiency in Test results is observed, PMC shall convey it to DST for testing, rectification or corrective action. It may also be necessary to demolish the concerned work. | |
10 | Monitor Work Inspection Reports | PMC | It needs to be checked whether errors or pending works mentioned by the Consultant in his Inspection Report have been corrected or rectified before continuing with further work. | |
11 | Monitor Process Inspection Reports | PMC | It needs to be checked whether errors or observations mentioned by the Consultant in his Inspection Report for a particular stage have been corrected or rectified before continuing with further stage of the process. | |
12 | Monitor Quality Certifications | PMC | Keep track of Certifications of Work as and when important works are Completed. | |
13 | Intimate Safety Lapses to Dev | PMC | Points to be reported: Unsafe access, Not Using Safety Gear, Safety Hazards etc. | |
14 | Monitor Progress of Work | PMC | Progress of work to be monitored w.r.t. Dev’s Detailed Project Schedule: Activities Completed, Activities In Progress and Activities Not yet Started. Delay, if any, to be identified for each Activity. Weekly status of work can also be seen from Dev's Weekly Progress Report. | |
15 | Scrutinize New Material/ Process Proposed by Dev | PMC | Scrutinize request received from the Dev based on the Process Statement, Specs, Samples received, Test Reports, Demo etc and advise MC whether the same can be used in place of the Material/ Brand/ Spec/ Process specified in the DA/ Tender Doc. | |
16 | Certify Achievement of Milestone | PMC | Scrutinize request received from the Dev and Certify Milestone for which Bank Guarantee, Lien on Sale Area is to be released. Soc may release the Security only thereafter. | R |
17 | Scrutinize Deviation Proposed by Dev | PMC | Scrutinize request received from the Dev w.r.t. Contractual Terms and advise MC in respect thereof. | |
18 | Scrutinize Hindrance Reported by Dev | PMC | Scrutinize request received from the Dev w.r.t. Contractual Terms after verifying data presented by Dev and advise MC in respect thereof. Hindrances approved by PMC may only be considered for Extension of Time. | |
19 | Scrutinize Dev's Request for Extension of Time | PMC | PMC shall scrutinize Dev's request for extension of time and convey his recommendations to the Soc. Time Extension may also be considered on the basis of the Hindrance Register. | R |