PHASE WISE JOURNEY
Sr. No. | Step | By | Particulars | M/ R/ G |
---|---|---|---|---|
1 | Approve Materials, Fittings and Fixtures | MC | Each Material, Fitting and Fixture which is approved shall be identified with its Brand, Design, Shade, Texture, Pattern, Size. MC may seek PMC’s advice for approval. Samples of approved Materials, Fittings and Fixtures shall be preserved for reference. | R |
2 | Approve New Material/ Process Proposed by Dev | MC/ GB | MC may approve or reject a proposed New Material/ Process after considering PMC advice. Major Deviations may need GB approval. | R |
3 | Approve a Mock-up | MC | MC may approve or reject a Mock-up after its inspection. MC may seek PMC’s advice for approval. | R |
4 | Release Security for Milestone | MC | A Security such as Bank Guarantee, Lien on Sale Area etc may be released on certification of PMC that the corresponding Milestones has been achieved. | |
5 | Approve Deviation Proposed by Dev | MC/ GB | MC may approve or reject a requested Deviation from Contractual Terms after considering PMC advice. Major Deviations may need GB approval. | R |
6 | Approve Dev’s Request for Time Extension | MC | This approval shall be based on PMC’s recommendations in respect of the time extension on account of approved hindrances. Additional time may also be approved subject to some commercial and/ or operational conditions as per contractual provision. | R |
7 | Upload Progress on Soc Website | MC | Progress of work may be uploaded on Soc’s Website from time to time. | |
8 | Conduct SGBM, if necessary | MC | SGBM may be conducted depending on a requirement or situation. Due process of sending notice and MoM shall also be followed. |