PHASE WISE JOURNEY
Sr. No. | Milestone | Ref. | Particulars |
---|---|---|---|
1 | Issue LOI to Selected Dev | LOI may contain conditions regarding Dev's performance and shall be binding until DA is signed. | |
2 | Approve, Execute and Register DA | SGBM | True copy of the registered DA to be provided to Soc. PoA to be issued to the Dev thereafter. |
3 | Finalization of Arch Plans by MC | This Finalization is mainly for the Members’ units, Amenities, Car parks and Floor heights. | |
4 | Approval of Proposal Plans & Allotment | SGBM | Complete plans to be approved by General Body. New units shall also be alloted. |
5 | Submit Plans to Statutory Authorities | Plans approved by General Body only shall be submitted to approving authorities. | |
6 | Obtain & Report Approvals/ Permissions of Plans | Such Approvals/ permissions may come in multiple stages. | |
7 | Execute and Register PAAA | This includes payment of Stamp duty and Registration by Dev. | |
8 | Issue Letter to Enter to Dev | This letter shall entitle the Dev to demolish existing building/s and Start construction of New bldg/s. | |
9 | Obtain Commencement Certificate | Copy of CC to be provided to MC and PMC. |