PHASE WISE JOURNEY
| Sr. No. | Record | By | Notes |
|---|---|---|---|
| 1 | Documents for Handover | Dev | Dev should submit docs as per PMC's List. |
| 2 | Letter of possession for Building & Common Amenities | MC | To be issued after the Building & Amenities are completed in all respect and are ready for use. |
| 3 | Project Conclusion Meeting (Minutes) | PMC | Meeting - Status of Completion of work, Contractual obligations etc. |
| 4 | Project Completion Report | PMC | This Report will mark end of Scope of PMC's work. |
| 5 | Letter of Closure of PMC Services | MC | To be issued on receipt of Project Completion Report. |
| 6 | Request for Confirmation of Completion of Dev's Work | Dev | Dev may send this letter after completion of all work but before demobilization from the site. |
| 7 | Letter Confirming Completion of Dev's Work | MC | Final Document after which Dev shall demobilize from the site and hand over the site back to Soc. |