PHASE WISE JOURNEY
| Sr. No. | Guideposts |
|---|---|
| 1 | List of Documents to be handed over by Developer: a) Approval docs, Permissions, NOCs and Plans b) As Built Drawings (Arch, Struct, MEP) c) Quality Certifications d) Maintenance Contracts and/ or Warrantees of Equipment, Services and Amenities e) Technical catalogues f) Operation and Maintenance manuals of Equipments and Amenities |
| 2 | Demonstrations of Equipments & Systems: a) Passenger Lifts and Car Lifts b) Parking System (if Mechanical type) c) Fire Fighting System d) Plumbing System e) DG Set (if provided) |
| 3 | Agenda Points for Project Closure Meeting: 1. Status of Work and Balance Formalities 2. Status of Contractual obligations by Dev & Soc as per DA 3. Status of Handing over Documentation 4. Unresolved issues 5. Start of Defect Liability Period 6. Formalities pertaining to New purchasers 7. RERA Compliance |
| 4 | Contents of PMC's Project Completion Report: 1. Project Summary 2. Important Milestones Completed 3. List of Project Documentation: - Communication Records - Project Review Reports - Project Review Meetings - Site Visits Reports 4. Documentation at the Stage of Handover - Balance/ Rectification Work - External - Balance/ Rectification Work - Internal (Members' Units) - Balance Handing Over Docs |